Construction Cost & Data
CONSTRUCTION
COST & DATA
- Earthwork Excavation upto 1.5m Depth - Rs.15/- per cu.ft
- Sand Filling to the
Foundation Trenches - Rs.50/-
per cu.ft
- Laying PCC 1:5:10 in
Foundation -
Rs.175/- per cu.ft
- Laying RCC 1:1.5:3 for
Foundation - Rs.400/- per cu.ft
- RCC 1:2:4 for Column,
Plinth Beam & Roof -
Rs.350/- per cu.ft
- Steel (Cutting,
Binding Fabrication) -
Rs.65/- per kg
- Construction Brick
Masonry CM 1:6 -
Rs.200/- per cu.ft
- Plastering Internal
Wall CM 1:5 -
Rs.60/- per sq.ft
- Plastering External
Wall CM 1:4 -
Rs.65/- per sq.ft
- Carving Plastering (Band/Architecture) -
Rs.200/- per r.ft
- Plastering Internal
Wall CM 1:5 -
Rs.60/- per sq.ft
- Electrical - Rs.150/- per sq.ft
- Plumbing - Rs.150/- per sq.ft
- Laying Mangalore Tile
with 2” muddy in CM 1:4 - Rs.150/-
per cu.ft
- Laying Vitrified Tile with
CM 1:5 -
Rs.150/- per sq.ft
- Kitchen Top with 20mm
tk -
Rs.300/- per sq.ft
- Underground Sump /
Over Head Tank
- (4½” BW & 4½” RCC wall) Tile Finish - Rs.23/- per L
- Joinery
o I quality Teak Main Door - Rs.750/- per sq.ft
o Flush Door - Rs.350/-
per sq.ft
o UPVC Windows - Rs.600/-
per sq.ft
o PVC Door -
Rs.3000/- per No.
- Painting
o ACE & Tractor Emulsion -
Rs.125/- per sq.ft
o ACE Shyne & Tractor Shyne / Premium - Rs.150/- per sq.ft
o Royale & Apex Ultima - Rs.175/- per sq.ft
o Royale Shyne & Apex Ultima - Rs.190/- per sq.ft
- MS Fabrication
o Pipe Gate - 2.75kg per sq.ft
o Grill Gate - 2.50kg per sq.ft
o Pipe Gate - Rs.110 per kg
o Grill Gate - Rs.75 per kg
o MS Hand Rail (Balcony/Staircase) -
Rs.250/- per r.ft
o SS Hand Rail (Balcony/Staircase) - Rs.1000/- per r.ft